Another busy week of construction along Manchester Road in Derry
DERRY — As summer begins to wind down, several major projects along Manchester Road continue along on schedule.
The widening of the road itself is still on pace to be completed by the end of November, according to Mike Fowler, public works director.
This week’s work along the road includes the overnight water shutdown at the intersection of Linlew and Manchester Road as drainage construction continues north of Linlew Drive and at the Tsienneto Road intersection. Roadway widening is scheduled at Ashleigh Drive, as is a signal conduit and foundation installation, according to Fowler.
During the week, there will be daytime lane shifts to accommodate the roadway widening and signal and drainage construction, which could result in minor delays.
“Drainage and signal work crossing intersections may require detail officers or flaggers to override normal traffic flow causing minor delays,” Fowler stated.
The current work along Manchester Road is part of the second phase of the project.
“All traffic is shifted into newly striped lane configurations along the westerly side (of the road),” according to Fowler. “This will allow the contractor to widen the road and build sidewalk along the easterly side mostly outside of traffic, which should help to reduce traffic delays from construction activities.”
The widening of the road is expected to continue to spur economic development in the TIF district that runs northerly on Manchester Road from Ross’ Corner to the Londonderry town line.
The total project cost is about $5.1 million, with the net amount bonded of $3.4 million. When the project originated in 2006, the projected cost was $6.5 million with authorized bonding of $5.4 million.
One of the biggest commercial projects in the district, the construction of a new Super Walmart on Ashleigh Drive, is expected to be completed and ready for the store to open in September, according to town administrator John Anderson.
Although there have been some rumors that the store could be opening sooner, Anderson said the Super Walmart continues to be on target for September.
While he has heard nothing solid about an agreement on the existing Walmart on Manchester Road, Anderson said he expects Walmart to actively market the property. Regardless, he said, the property will remain on the town’s tax rolls.
aswift@newstote.com
The widening of the road itself is still on pace to be completed by the end of November, according to Mike Fowler, public works director.
This week’s work along the road includes the overnight water shutdown at the intersection of Linlew and Manchester Road as drainage construction continues north of Linlew Drive and at the Tsienneto Road intersection. Roadway widening is scheduled at Ashleigh Drive, as is a signal conduit and foundation installation, according to Fowler.
During the week, there will be daytime lane shifts to accommodate the roadway widening and signal and drainage construction, which could result in minor delays.
“Drainage and signal work crossing intersections may require detail officers or flaggers to override normal traffic flow causing minor delays,” Fowler stated.
The current work along Manchester Road is part of the second phase of the project.
“All traffic is shifted into newly striped lane configurations along the westerly side (of the road),” according to Fowler. “This will allow the contractor to widen the road and build sidewalk along the easterly side mostly outside of traffic, which should help to reduce traffic delays from construction activities.”
The widening of the road is expected to continue to spur economic development in the TIF district that runs northerly on Manchester Road from Ross’ Corner to the Londonderry town line.
The total project cost is about $5.1 million, with the net amount bonded of $3.4 million. When the project originated in 2006, the projected cost was $6.5 million with authorized bonding of $5.4 million.
One of the biggest commercial projects in the district, the construction of a new Super Walmart on Ashleigh Drive, is expected to be completed and ready for the store to open in September, according to town administrator John Anderson.
Although there have been some rumors that the store could be opening sooner, Anderson said the Super Walmart continues to be on target for September.
While he has heard nothing solid about an agreement on the existing Walmart on Manchester Road, Anderson said he expects Walmart to actively market the property. Regardless, he said, the property will remain on the town’s tax rolls.
aswift@newstote.com
- David Harsanyi: Get the IRS out of the speech business altogether - 9
- Another View -- Ryan Gallagher: The U.S. government spies on reporters all too frequently - 4
- John Stossel: Who has true grit anymore? - 0
- Another View: New Hampshire would take a risky bet on casinos - 6
- Ramesh Ponnuru: In flextime fight, liberals play to their stereotype - 0
- Jonah Goldberg: Benghazi's smoking guns - 1
- Another View: Nashua does need to conduct its own review of commuter rail - 1
- George Will: Forgetting the lessons of Watergate - 0
- Charles Arlinghaus: Screeching lies does not count as debate - 2
Charles Krauthammer: Redacted truth, subjunctive outrage
READER COMMENTS: 0- Man shot to death on Manchester street late Saturday - 2
- UNH hires firm to redesign one of its logos - 10
- Disengaged: Obama's lousy excuse - 11
- Underestimating NH: Gun control picks two wrong targets - 17
- Roaming jihadis: A terrorist visits Manchester - 3
- Ted Siefer's City Hall: School board on the defensive over Cupcake-gate - 1
- Garry Rayno's State House Dome: All eyes on House as casino vote nears - 2
- 43 killers on lifetime parole - but where? - 3
- Official says NH abortion sites need state scrutiny - 13
NY man stable after destroying classic Porsche 911 in Route 16 wreck
READER COMMENTS: 1- Should adultery remain a crime under U.S. military law?
- Yes
- 42%
- No
- 58%
- Total Votes: 641